1900 Broadway

1900 Broadway May 2021 Project Update

Progress Summary As of May 2021, Over 490 jobs are projected to have been created to date from design, construction, and procurement, satisfying the minimum EB-5 job creation requirements for 49 EB-5 investors. Excavation on site has reached a depth of 30 feet Over 100 trucks per day off hauling soil (at peak production) View ...

Suffolk Construction 1900 Broadway Progress Newsletter May 2020

PROJECT: 1920 - 1950 Broadway DEVELOPER: 1900 BWAY TOWER DEVELOPMENT ARCHITECT: SCB Architects CONTRACTOR: Suffolk CONSTRUCTION SCHEDULE   Shoring & Excavation: March 2020 – Jan 2021 Foundations & Structure: Nov 2020 – Jan 2022 Exterior Building Finishes: May 2021 – March 2022 Interior Build-Out: March 2022 – Jan 2023 Substantial Completion: Jan 2023 WORK HOURS ...