Progress Summary As of May 2021, Over 490 jobs are projected to have been created to date from design, construction, and procurement, satisfying the minimum EB-5 job creation requirements for 49 EB-5 investors. Excavation on site has reached a depth of 30 feet Over 100 trucks per day off hauling soil (at peak production) View ...
PROJECT: 1920 - 1950 Broadway DEVELOPER: 1900 BWAY TOWER DEVELOPMENT ARCHITECT: SCB Architects CONTRACTOR: Suffolk CONSTRUCTION SCHEDULE Shoring & Excavation: March 2020 – Jan 2021 Foundations & Structure: Nov 2020 – Jan 2022 Exterior Building Finishes: May 2021 – March 2022 Interior Build-Out: March 2022 – Jan 2023 Substantial Completion: Jan 2023 WORK HOURS ...