Construction Update

May 9th, 2018 Periodic Construction Update for the Graduate, a 260-unit student housing apartment tower in Downtown San Jose.

Project Update

The Graduate is making steady progress toward a Spring 2020 opening:

  • Concrete complete on all 19 floors
  • Glass window wall facade nearing complete install
  • Mechanical equipment’s being installed on the rooftop
  • Aluminum accent panel installation nearing substantial completion  Expended
  • Interior fit-out in progress (moving from lowest floors up through the tower in sequence)
  • Off-site leasing office space identified
  • Marketing and leasing programs furthering development, website in progress, graphic collateral progressing and campaigns being designed for initial launch in 2020

Job Creation Update

The Graduate is making steady progress toward a Spring 2020 opening:

  • Concrete complete on all 19 floors
  • Glass window wall facade nearing complete install
  • Mechanical equipment’s being installed on the rooftop
  • Aluminum accent panel installation nearing substantial completion  Expended
  • Interior fit-out in progress (moving from lowest floors up through the tower in sequence)
  • Off-site leasing office space identified
  • Marketing and leasing programs furthering development, website in progress, graphic collateral progressing and campaigns being designed for initial launch in 2020

EB-5 Update

The Graduate is making steady progress toward a Spring 2020 opening:

  • Concrete complete on all 19 floors
  • Glass window wall facade nearing complete install
  • Mechanical equipment’s being installed on the rooftop
  • Aluminum accent panel installation nearing substantial completion  Expended
  • Interior fit-out in progress (moving from lowest floors up through the tower in sequence)
  • Off-site leasing office space identified
  • Marketing and leasing programs furthering development, website in progress, graphic collateral progressing and campaigns being designed for initial launch in 2020

Construction Update

The Graduate is making steady progress toward a Spring 2020 opening:

  • Concrete complete on all 19 floors
  • Glass window wall facade nearing complete install
  • Mechanical equipment’s being installed on the rooftop
  • Aluminum accent panel installation nearing substantial completion  Expended
  • Interior fit-out in progress (moving from lowest floors up through the tower in sequence)
  • Off-site leasing office space identified
  • Marketing and leasing programs furthering development, website in progress, graphic collateral progressing and campaigns being designed for initial launch in 2020

Operations Update

The Graduate is making steady progress toward a Spring 2020 opening:

  • Concrete complete on all 19 floors
  • Glass window wall facade nearing complete install
  • Mechanical equipment’s being installed on the rooftop
  • Aluminum accent panel installation nearing substantial completion  Expended
  • Interior fit-out in progress (moving from lowest floors up through the tower in sequence)
  • Off-site leasing office space identified
  • Marketing and leasing programs furthering development, website in progress, graphic collateral progressing and campaigns being designed for initial launch in 2020